NO |
PROJECT TITLE |
CLIENT |
START |
ESTIMATE COMPLETION DATE |
WORKDONE |
REMARKS |
1 |
PROPOSED PIPE REPLACEMENT
PROGRAM IN SELANGOR, WILAYAH PERSEKUTUAN KUALA LUMPUR AND PUTRAJAYA YEAR 2021
PACKAGE 45A- HULU LANGAT |
PENGURUSAN AIR SELANGOR SDN BHD |
Thursday, 15
July, 2021 |
Friday, 14 October, 2022 |
75% |
ON-GOING |
2 |
PELANTIKAN
KONTRAKTOR PANEL BAGI KERJA-KERJA PEMBAIKIAN DAN PENYENGGARAAN PAIP SERTA
KERJA-KERJA MENUTUP DAN MENYAMBUNG
SEMULA BEKALAN AIR MENGGUNAKAN KAEDAH "PLUG FERRULE" - KLANG |
PENGURUSAN AIR
SELANGOR SDN BHD |
Saturday, 1 January,
2022 |
Saturday, 31 December, 2022 |
TBC |
ON-GOING |
3 |
PROPOSED PIPE REPLACEMENT
PROGRAM IN SELANGOR, WILAYAH PERSEKUTUAN KUALA LUMPUR AND PUTRAJAYA YEAR
201/2018 (CONTINUATION FOR COMPLETION OF PROJECT) ; PACKAGE 7-SEPANG |
PENGURUSAN AIR
SELANGOR SDN BHD |
Monday, 28 March,
2022 |
Tuesday, 27 June, 2023 |
58% |
ON-GOING |
4 |
LRT 3 - STATION
15 |
SUNWAY |
Monday, 31 October,
2022 |
Saturday, 30 September, 2023 |
90% |
ON-GOING |
5 |
LRT 3 - STATION
8, 9,10 |
GABUNGAN
STRATEGIK SDN BHD |
Friday, 6 August,
2021 |
Thursday, 30 June, 2022 |
45% |
ON-GOING |
6 |
KAJANG SILK |
GAGASAN MAYA SDN
BHD |
Saturday, 9 December,
2023 |
Thursday, 1 February, 2024 |
80% |
ON-GOING |
7 |
PROPOSED PIPE
REPLACEMENT PROGRAM IN SELANGOR,WILAYAH PERSEKUTUAN KUALA LUMPUR AND
PUTRAJAYA YEAR 2022 PACKAGE 78-GOMBAK |
PENGURUSAN AIR
SELANGOR SDN BHD |
Monday, 28 August,
2023 |
Wednesday, 27 November, 2024 |
0% |
ON-GOING |
8 |
PROPOSED
DEVELOPMENT OF SG RASAU WATER SUPPLY SCHEME (STAGE 1), SELANGOR DARUL EHSAN .
PACKAGE 3 - DESIGN AND BUILD OF PROPOSED NEW BUKIT LIPAT KAJANG BOOSTER
STATION, RESERVOIRS AND ASSOCIATED WORKS |
TALIWORKS
CONSTRUCTION SDN BHD |
Monday, 25 September,
2023 |
Tuesday, 24 September, 2024 |
22% |
ON-GOING |
9 |
MENAIKTARAF
JALAN PERSEKUTUAN FT3210 DARI PERSIMPANGAN BATU 9 KE PERSIMPANGAN JALAN DATO
ALIAS TERMASUK PEMBINAAN JEJAMBAT MERENTASI PERSIMPANGAN BATU 9 CHERAS DAERAH
HULU LANGAR SELANGOR |
SYARIKAT
PERNIAGAAN MONZA SDN BHD |
Wednesday, 1
November, 2023 |
Friday, 30 August, 2024 |
15% |
ON-GOING |
10 |
PROPOSED
DEVELOPMENT OF SG RASAU WATER SUPPLY SCHEME (STAGE 1), SELANGOR DARUL EHSAN .
PACKAGE 2 - DESIGN AND BUILD OF PROPOSED NEW BUKIT LIPAT KAJANG BOOSTER
STATION, RESERVOIRS AND ASSOCIATED WORKS |
TALIWORKS
CONSTRUCTION SDN BHD |
Tuesday, 2 January,
2024 |
Monday, 1 July, 2024 |
5% |
ON-GOING |
11 |
PROPOSED
DEVELOPMENT OF SELANGOR BIO BAY PHASE 1A, PULAU INDAH, MUKIM KLANG SELANGOR
DARUL EHSAN FOR CENTRAL SPECTRUM (M) SDN BHD " CIVIL INFRASTRUCTURE
WORKS" |
PEMBINAAN TEGAP
TUNAS SDN BHD |
Monday, 17 July, 2023 |
Sunday, 17 September, 2023 |
75% |
ON-GOING |
12 |
SUPPLY, DELIVER,
INSTALL, TESTING AND COMMISSIONING FOR COLD WATER & SANITARY PLUMBING
SERVICES FOR LSS4-GOPENG & KAMPAR PROJECT |
SUNWAY
CONSTRUCTION SDN BHD |
Saturday, 30
September, 2023 |
Monday, 1 April, 2024 |
85% |
ON-GOING |